Case studyOffices and fleetHamm

100+ chargers, one campus

The campus at 4, rue de Bitbourg houses BALTHASAR Group, several companies and our own office and showroom. More than 100 chargers run on nested load management: the campus, each building and each tenant has its own limit.

Last reviewed:

chargers on the campus
100+
chargers on the campus
for one tenant's vans, office and warehouse
125 A
for one tenant's vans, office and warehouse
the vans' charging window
15–06 h
the vans' charging window

The project

What was built

Site
Business campus, Luxembourg-Hamm: offices, warehouses, fleet vehicles, staff and visitors
Chargers
More than 100 VOOL chargers
Load management
Multi-level and multi-point: several VOOL load management controllers, one for the campus connection and one for each building or tenant, with patented phase switching
One tenant
A delivery company: its vans, its office and its warehouse share a 125 A connection
Charging window
The vans are parked from 15:00 to 06:00; the controller spreads their charging over that time
Operation
AMP X VOLT: platform, billing per charge point, support

125 A

for a delivery fleet, its office and its warehouse

The vans have fifteen hours to charge, so the controller never lets the site's peak rise. A low peak keeps the power-based part of the grid fees low: thousands of euros saved every year, with every van full by 06:00. See grid fees.

What it shows

Load management in levels

A campus has one grid connection, and each building and tenant has its own limit below it. Each controller manages its level and passes on what is left, so one tenant's peak never takes power from another and the campus connection is never crossed.

Most car parks are sized as if every charger ran at full power at once. They never do: cars arrive at different times, need different amounts and leave at different times. See it in the live demo or read about load management.